Rialto Court, St Austell: a curved cream rendered Art Deco style block with porthole windows and railings

Section 20 Notices and Consultation, Explained

A Section 20 notice is the written notice a landlord or management company must give leaseholders before major works that would cost any one of them more than £250, or before a contract of more than twelve months that would cost any one of them more than £100 in an accounting period. It starts Section 20 consultation, the process the Landlord and Tenant Act 1985 requires before those costs can be recovered in full. This is what triggers it, what the notices are for, what happens if it is skipped, and what we charge to run it.

ISO 9001:2015 certifiedAward-winningThe Property Ombudsman

Last updated by the Plymouth Block Management team.

When Must a Section 20 Notice Be Issued?

Section 20 consultation applies when qualifying works would cost any one leaseholder more than £250, or when a qualifying long-term agreement would cost any one leaseholder more than £100 in any accounting period. Section 20 of the Landlord and Tenant Act 1985 and the Service Charges (Consultation Requirements) (England) Regulations 2003 set out the consultation that has to be carried out before those costs can be passed on in full through the service charge.

Qualifying worksOver £250 per leaseholder
Long-term agreementOver £100 per leaseholder a year
Observation period30 days, twice
If skippedRecovery capped

A qualifying long-term agreement is a contract of more than twelve months, so a lift maintenance contract or a grounds maintenance contract can require consultation even though no single visit is expensive. The consultation is about the process, not about permission: leaseholders are entitled to be told what is proposed and to have their observations considered, and the landlord still makes the decision.

Once a qualifying long-term agreement is in place, qualifying works carried out under it follow a shorter route set by Schedule 3 of the 2003 Regulations: one notice describing the works and stating the total estimated cost, 30 days for written observations, and a written response within 21 days to anyone who made them. Schedule 3 does not require further estimates to be obtained.

What Are the Three Section 20 Notices?

Where no public notice is required, Section 20 consultation runs in three stages: a Notice of Intention with 30 days for observations, a Statement of Estimates with at least two estimates and a further 30 days, and, where the contract does not go to the lowest estimate or a leaseholder’s nominee, a Notice of Reasons within 21 days of entering the contract. Missing any of them is what puts recovery at risk.

1. Notice of Intention

The Regulations set out what the first notice must contain rather than a standard form. It must:

  • describe the works in general terms, or say where and when a description can be inspected
  • give the reasons the works are considered necessary
  • invite written observations and give the address they should be sent to
  • state that observations must arrive within the 30-day period, and the date that period ends
  • invite each leaseholder to propose a contractor from whom an estimate should be sought

Leaseholders have 30 days to respond and may nominate a contractor they would like asked to quote.

2. Statement of Estimates

At least two estimates are obtained, one of them from a contractor wholly unconnected to the landlord, and a nominee proposed by leaseholders must be approached. The estimates are made available with a second notice, and there is a further 30 days for observations.

3. Notice of Reasons

Where the contract does not go to the lowest estimate or to a leaseholder's nominee, a third notice explains the reasons for the choice and responds to the observations received. It is issued within 21 days of entering the contract.

Section 20 Consultation Process and Timeline

For qualifying works that do not need public notice, the 2003 Regulations set the order. Each notice goes to every leaseholder who will contribute and to any recognised tenants’ association.

Section 20 consultation steps and time allowed
StepWhat happensTime allowed
Notice of IntentionThe works and the reasons for them are described; leaseholders are invited to send written observations and to nominate a contractor30 days, beginning with the date of the notice
EstimatesAt least two estimates are obtained, one from a contractor wholly unconnected with the landlord, and any leaseholder nominee is approachedNo fixed period
Statement of EstimatesAt least two estimates are set out with a summary of the observations and the responses, and all the estimates are open for inspectionA further 30 days, beginning with the date of that notice
Notice of ReasonsNeeded only if the contract does not go to the lowest estimate or a nominee; it explains the choice and responds to observationsWithin 21 days of entering the contract
DispensationWhere a step cannot be followed, or was missed, the First-tier Tribunal can dispense with some or all of the requirements under section 20ZABefore or after the works

Received a Section 20 Notice? What to Do Next

  1. Check which notice it is. A Notice of Intention asks for observations and contractor nominations, a Statement of Estimates asks for observations on the estimates, and a Notice of Reasons explains why the contract did not go to the lowest estimate or a leaseholder’s nominee.
  2. Note the closing date. The first two notices must each state the date their 30-day period ends, and observations need to arrive by then.
  3. Send your observations in writing to the address on the notice. The landlord must have regard to observations made in time, and responses to those on the first notice are summarised in the Statement of Estimates.
  4. Nominate a contractor at the first stage if you know one who should be asked to quote.
  5. Inspect all of the estimates at the second stage, at the place and hours the notice gives, not only the two set out in the statement.
  6. If you think the cost is unreasonable or the consultation was not followed, the First-tier Tribunal (Property Chamber) can decide; see challenging a service charge at tribunal.

What Happens If Section 20 Consultation Is Not Carried Out?

The sanction falls on recovery, not on the works. If the consultation requirements are not met and no dispensation is granted, the amount recoverable from each leaseholder is capped at £250 for qualifying works, or £100 in an accounting period under a qualifying long-term agreement, whatever the work actually cost. The difference stays with the landlord.

Section 20ZA lets the First-tier Tribunal dispense with the requirements. Since Daejan Investments Ltd v Benson [2013] UKSC 14 the question the tribunal asks is what prejudice the leaseholders actually suffered because of the failure, rather than how serious the breach looks in itself, and dispensation is regularly granted on conditions. It is not a formality and it is not free, which is why it is better used for genuine emergencies than as a way of catching up.

What Do We Charge to Run Section 20 Consultation?

Our Section 20 management fee is 4 to 10 per cent of total project cost, or £180, and a Section 20ZA application is £180, both from our published price list. Major works are charged separately from the management fee, and the rate is published rather than quoted case by case. The percentage reflects the scale and complexity of the project; the flat fee applies to the smaller schemes where a percentage would not cover the work. Both figures are in the price list below, which is the same document published on our policies page.

Contractor costs, professional fees for a surveyor or contract administrator where one is needed, and any tribunal fees are separate and are shown as their own lines in the consultation documents rather than absorbed into ours.

Section 20 Questions

What Counts as Major Works?

There is no list of qualifying jobs. The test is the cost, not the label. If the work would leave any single leaseholder contributing more than £250 through the service charge, it is qualifying work and the consultation applies, whether that is a roof, a lift, redecoration or a drainage repair.

Can I Refuse to Pay a Section 20 Major Works Charge?

Not on the basis of disagreeing with the decision. What the lease requires you to pay, you pay. What you can do is test whether the charge is reasonable and whether the consultation was carried out properly. Both are questions for the First-tier Tribunal (Property Chamber), and it is designed to be used without a solicitor. If the landlord did not consult properly and has no dispensation from the tribunal, the amount it can recover from each leaseholder for those works is capped at £250.

Can I Put Forward My Own Contractor?

Yes. The Notice of Intention invites nominations, and a contractor nominated by leaseholders has to be approached for an estimate. Nominating one does not oblige anyone to appoint them, but if they are not appointed the reasons have to be given in writing.

Do Leaseholders Have to Agree to Major Works?

No. Consultation gives leaseholders the right to be told what is proposed, to have their observations considered and, in most cases, to nominate a contractor, but the decision stays with the landlord or management company. Whether the cost is reasonable is a question the First-tier Tribunal can decide.

Does the Reserve Fund Pay for It?

Where the lease provides for a reserve fund and there is money in it, that is what it is for, and drawing on it reduces or removes the one-off demand. The consultation still has to happen: the threshold is about what each leaseholder contributes to the works, not about which pot the money comes out of.

How Long Does the Process Take?

The two observation periods are 30 days each and they are minimums, so the consultation itself is rarely shorter than about three months before a contract can be entered into. Specifying the work, obtaining estimates and scheduling a contractor sit on top of that. Emergency works that cannot wait are a separate question, and they are where a section 20ZA application usually arises.

Can the Landlord Split the Work Up to Stay Under £250?

No. Artificially dividing a single scheme into parcels to dodge the threshold is not a route round the regulations, and a tribunal looks at the substance of what was done.

Can I Be Charged for Costs Incurred More Than 18 Months Ago?

Usually not. Under section 20B of the Landlord and Tenant Act 1985, a cost incurred more than 18 months before it is demanded cannot be recovered unless, within those 18 months, leaseholders were told in writing that the cost had been incurred and that they would be required to contribute to it.

I Am Buying a Flat with a Section 20 Notice. Who Pays?

The lease decides who pays, which is usually whoever owns the flat when the demand is issued. A live consultation shows up in the LPE1 management pack, and buyer and seller normally agree through their solicitors who bears the cost, often with a retention from the sale price.

When Do I Have to Pay a Major Works Demand?

When the lease says, once a valid demand has been issued. Many leases allow major works to be demanded in advance, on account, so the 18-month rule above does not stop a demand made before the work is done.

Where We Fit

For the developments we manage we specify the work with the board, obtain the estimates, issue and track the notices, collate the observations and answer them, and hold the contractor to the programme once work starts. Where a scheme needs a surveyor or a contract administrator we help the board appoint one; we do not carry out the design or the construction ourselves.

If you are a director of a resident management company facing a first major works project, or a leaseholder who has had a notice and wants to understand it, talk to us. If your question is about a figure on a statement you have already had, the accounts team is the faster route.

Service Charge & Accounts Queries

Questions about a service charge demand, your statement, a payment or the year-end accounts go straight to our accounts team rather than through general enquiries.

Email accounts@plymouthblockmanagement.com

Quoting your development and flat number gets an answer fastest. If your query is about a cost you want explained, say which line on the statement and we will come back with the invoice behind it. Leaseholders also have a statutory right to a summary of costs under section 21 of the Landlord and Tenant Act 1985.

Fields marked * are required.

Thank you. Your query has been sent to the accounts team.